Excavation and shoring is now complete on both parcels of the Riverside in Pine Grove site. Framing on the south parcel is nearly complete, with sanitary, storm drain, and below grade plumbing work in the south parcel parking garage ongoing.
The slab on grade and suspended slab are complete on the north parcel, and framing is expected to commence shortly. Construction on both parcels is progressing well, with site clearance completed, the relocation of the heritage house completed, and substructure work nearly completed on both parcels. First occupancies are expected to take place in late 2017.
Images: Construction progress on South Parcel as of May 2017
Images. Construction progress on North Parcel as of May 2017